"The thermal power plants including coal-fired ones, and hydro power plants will be constructed expeditiously according to the generation plans of the Ceylon Electricity Board, while taking into consideration the social problems and environmental implications".
Mahinda Chintana |
At
present,
it is
estimated
that 77%
of the
households
have
electricity
with
grid
connections
whilst
3% are
served
by
off-grid
facilities.
The
annual
increase
in
demand
for
electricity
is
around
7%-8%.
Therefore,
around
200MW
needs to
be added
to the
system
annually.
Electricity
generation
in Sri
Lanka
depends
heavily
on crude
oil.
Thus,
the
power
generation
cost has
increased.
In order
to
overcome
this
situation,
low cost
electricity
generating
facilities,
such as
coal and
hydro
electric
power
plants
are
being
constructed.
As
mentioned
in 'Mahinda
Chintana',
President
Mahinda
Rajapaksa
has
given
high
priority
to
energy
security
and
energy
conservation
in the
country.
Upper
Kotmale
hydropower
project
This
project
was
delayed
due to
various
reasons
under
several
governments
until
the
present
government
took a
firm
decision
to
commence
the
project
in 2006.
It is
expected
to add
409 GWh
to the
national
grid
annually
and help
meet the
future
electricity
demand
of the
country.
The (UK)
dam will
be
located
near
Talawakele
and an
underground
powerhouse
at
Niyagammodara.
These
will be
linked
by a
tunnel.
The
project
area
covers
around
540
square
kms of
the
upstream
catchment
of the
Kotmale
Oya. The
total
estimated
cost of
the
project
is Rs.
38,219
million.
It is
expected
to be
completed
by
December
2010.
This
project
will
save
foreign
exchange
that is
currently
utilized
for
importing
diesel
for
thermal
power
generation.
The
Ceylon
Electricity
Board (CEB)
spends
approximately
Rs.
16,000
million
on
importing
diesel
for
power
generation.
A
considerable
portion
of this
expenditure
can be
saved as
a result
of the
Upper
Kotmale
hydropower
project.
It is
also
expected
to
provide
direct
and
indirect
employment
and
income
earning
opportunities
to many
unemployed
persons
during
its
construction
period.
The
electricity
generated
by this
power
plant
can be
utilized
to
better
serve
the
demands
of the
Industrial
Sector.
A
reliable
and
efficient
power
supply
will
ensure
safety
for
investors
who hope
to
invest
in
industrial
development
projects.
This in
turn
will
lead to
development
of the
Industrial
Sector
in the
country.
The
power
from
this
project
will be
useful
to
provide
electricity
to
regions
where
electricity
supply
is
currently
not
available.
At
present
20% of
the
total
households
in the
country
does not
have
access
to
electricity.
A part
of this
population
will
receive
electricity
through
this
project.
The
contract
for
preparatory
work
between
CEB and
Maeda
Corporation,
Japan
was
signed
in July
2005.
Under
this,
access
roads
and
permanent
facilities
for
re-settlers
are in
progress.
The
construction
of
permanent
facilities
for
employees
and
engineers
is
complete.
Two 33
KV
transmission
lines
have
also
been
completed,
while
laying
concrete
for the
intake
dam and
river
bank
protection
work are
in
progress.
In
addition,
the
excavations
for the
access
tunnel
and
cable
tunnel
have
been
completed,
as well
as the
coffer
dam in
the
outlet
area is
also
completed,
while
the
excavation
of lower
inclined
penstock
pilot
tunnel
is in
progress.
The
construction
of 220
Kv
transmission
line is
also in
progress.
Kerawalapitiya
Thermal
Power
Plant
Adding
another
power
source
to the
national
grid,
the
Kerawalapitiya
Thermal
Power
Plant
was
opened
in
December
2008 by
President
Mahinda
Rajapaksa.
The 200
megawatt
power
plant,
built at
a cost
of US$
300
million,
expanded
production
to 300
megawatts
within a
year,
and also
promotes
socio-
economic
development
in
Kerawalapitiya
and
neighbouring
towns.
Development
and
Improvement
of
Transmission
Systems
The
implementation
of
transmission
development
activities
is
expected
to
ensure a
reliable
power
supply
and
reduce
transmission
losses
of the
national
grid.
The key
components
of the
project
are the
construction
of
Katunayake
Grid
Sub-Station,
improvement
of the
Valachchenai
Transmission
Project,
augmentation
of
Colombo
A Grid
Sub-Station,
augmentation
of
Colombo
1 Grid
Sub-Station,
installation
of
220Kv/132
Kv
inter-bus
transformer
at
Rantembe
PS and
the
installation
of the
3rd
220/132
Kv
inter-bus
transformer
at
Biyagama.
Under
this
project
the
electrification
level of
the
country
increases
with the
expansion
of the
existing
power
distribution
capacity
and
improvement
of
transmission
facilities.
It
reduces
transmission
and
distribution
losses
from
15.5% to
12% of
net
generation,
and save
an
additional
capacity
of
electricity
which is
equal to
360Gwh
annually.
These
improved
transmission
facilities
provide
opportunities
to
connect
renewable
energy
power
plants
to the
national
grid.
This
will
encourage
private
investors
who will
positively
contribute
towards
developing
the
renewable
energy
sector
of the
country.
It will
also
improve
the
provision
of power
supply
to the
industrial
sector,
which
will in
turn
attract
investments.
Norochcholai
Coal
Fired
Power
Plant
Sri
Lanka is
expected
to give
a major
boost to
its
power
sector
with the
completion
of the
Norochcholai
coal
power
project.
The
first
phase of
the
construction
was
completed
in 2009
while
the
second
and
third
phases
of the
project,
aimed at
generating
over
600MW
will
commence
soon
with
financial
assistance
from the
Chinese
Government.
300 MW
is added
to the
national
grid
with the
completion
of the
first
stage
and 600
MW will
be added
in the
second
and
third
stages.
The
project
is
expected
to make
a
significant
contribution
towards
meeting
the
country's
electricity
needs by
2015.
The cost
of power
generation
from
coal
fired
power
plants
is
relatively
low
compared
to oil
fired
power
plants.
Thus,
this
project
will
result
in
saving a
considerable
amount
of
foreign
exchange
and
reduction
in the
cost of
power
generation.
The
project
is
expected
to
contribute
towards
the
expansion
of the
industrial
sector
as well
as other
development
sectors.
It will
thus
contribute
to
increased
employment
as well
as
income
generation
opportunities.
The
tariff
for
electricity
can be
reduced
due to
cost
effective
power
generation.
Trincomalee
Coal
Fired
Power
Plant
This
project
aims to
construct
a 500 MW
power
plant in
Trincomalee,
in the
East in
order to
generate
electricity
at a low
cost for
the
national
grid.
The cost
of power
generation
from
this
plant is
relatively
low
compared
to other
oil
fired
power
plants.
Therefore,
those
benefits
can be
transferred
to its
consumers.
The low
cost of
electricity
and
reduced
cost of
power
generation
will
meet the
increased
demand
for
electricity.
The
generated
electricity
of this
power
plant
can also
be
utilized
to meet
the
demand
of the
Industrial
Sector.
A
reliable
and
efficient
power
supply
is a
precondition
for the
present
development
process.
The
project
will
consist
two
phases
and the
first
phase is
expected
to be
completed
by 2012.
Through
these
projects
the
government
expects
to
provide
electricity
to the
entire
nation
especially
rural
areas to
uplift
the
living
standards
of the
people.
These
projects
will no
doubt
speed up
the
development
process
as well
so that
all
communities,
irrespective
of
ethnicity,
class,
religion
or
region
will
reap its
benefits.
|