The second phase of the Jeyaraj
Fernandopulle Memorial flyover constructed
on the Kandy Colombo road will be
commissioned today. The second phase of
the fly over at Kelaniya has been
constructed within 75 days under a concept
initiated by President Mahinda Rajapaksa.
The dual lane flyover to facilitate the
traffic flow at the Kelaniya level crossing
is 325 meters in length 7.4 meters in width.
The project has been completed at a cost of
Rs.1,050 million. The whole project
estimated to cost Rs. 2,100 million is
funded by the British Government.
The construction work of this flyover was
commenced on the initiative by former
Highways and Road development Minister
Jeyaraj Fernandopulle.
The first phase of the project was
completed within 61 days setting a world
record.
|