|
A
high-capacity
power
transmission
link
between
India
and Sri
Lanka
will
begin
construction
next
year and
will be
completed
by 2013.
The
285-kilometre
power
link,
including
submarine
cables
over a
stretch
of 50
km, will
enable
the two
countries
to trade
their
surplus
power,
thereby
offering
a
cheaper
option
to
bridge
their
power
generation
deficit
and also
manage
their
peak
demand.
The
transmission
link
will
pave the
way for
future
trading
of
electricity
between
the two
countries.
Powergrid
and the
Ceylon
Electricity
Board
will lay
down
cables
under
the Gulf
of
Mannar
between
Rameshwaram
in Tamil
Nadu and
Talaimannar
in
Mannar.
On
the
Indian
side,
the
cable
will be
connected
to the
southern
grid in
Madurai
through
an
overhead
transmission
line. On
the Sri
Lankan
side,
the
underwater
cable
will be
linked
to the
country's
power
network
in
Anuradhapura
through
an
overhead
line.
"The
work on
the
project
should
begin by
February-March
next
year
after
the MoU
is
signed.
It will
take us
two-and-a-half
to three
years to
complete
this
project,"
quoting
S K
Chaturvedi,
Chairman
and
Managing
Director
of
Powergrid,
Indian
Media
reported.
The
subsea
line
would
initially
have a
capacity
of 500
Mw,
according
to
Powergrid's
feasibility
report.
Later,
the
power
flow
could be
ramped
up to
1,000 Mw
by 2016
when the
power
generation
capacities
in the
two
countries
improve,
with
surplus
availability
especially
in
India's
southern
grid.
Powergrid
had
carried
out a
feasibility
study of
the
project
last
year and
had
found
the
installing
of the
transmission
lines to
be
feasible.
"We have
already
received
an
approval
from the
Ministry
of
External
Affairs
(MEA).
Now a
detailed
project
report
will be
prepared,"
said
Chaturvedi.
|