Friday, March 09, 2012 - 5.40 GMT
Second phase of oil exploration begins

 

The second phase of oil exploration in the Mannar Basin had begun and oil wells are likely to be drilled in 2013 after another round of seismic studies.

Cairn Lanka successfully completed the first phase of the exploration campaign on Sri Lanka’s side of the Mannar Basin on Block SL-2007-01-001 and has delivered two back to back discoveries.

The seismic survey will be followed by a technical evaluation of the data, data interpretation and then with another drilling campaign. An international tender for this seismic programme was floated by the company last year during the first phase of drilling campaign.

Cairn Lanka had spent over US$ 150 million in the first phase of the drilling campaign that resulted in two gas discoveries. The initial estimate for the programme was around US$ 110 million.

The drilling campaign in the second phase will be undertaken during the fair weather window. According to the scope of the international tender, the work programme will involve one firm well and have provisions for three optional wells too, in the Gulf of Mannar. It is likely to commence in 2013, post completion of data interpretation and other pre-drilling tests and studies.

Cairn Lanka has also floated an international tender inviting experienced services contractors to provide services for this deepwater drilling campaign.

The company has invited an international tender bid for the drilling operation. A series of stringent guidelines have been laid out for the contractors who need to comply with, and should have a successful track record to be considered. Special emphasis is also being laid on the contractor’s ability to adhere to the stringent health, safety and environmental management requirements.

The first phase of the exploration programme involved the acquisition, processing and interpretation of 1,753 sq km of 3D seismic data and a three well deep water drilling programme. The seismic programme exceeded the phase I commitment by 20% and the drilling programme exceeded the drilling depth commitment by 50%. The first phase of the programme resulted in two successive gas and condensate discoveries: the CLPL-Dorado-91H/1z well and, the CLPL-Barracuda-1G/1 well.




 
 
 
   
   
     
   
   

top

   

Contact Information:: Send mail to priu@presidentsoffice.lk with questions or comments about this web site.
Last modified: March 09, 2012.

Copyright © 2008 Policy Research & Information Unit of the Presidential Secretariat of Sri Lanka. All Rights Reserved.