Upper Kotmale to be completed in June

 

Ninety six percent of the construction of the Upper Kotmale hydro power plant which will generate 150 megawatts of electricity has been completed.

It already generates 75 megawatts and 150 megawatts will be added to the national grid by this June, Power and Energy Ministry sources said.

The power plant project commenced in 2006 to meet the increasing demand for electricity. The Japanese Government provided 37,817 million yen for the project. The Ceylon Electricity Board spent Rs 8,548 million on the project.

The Upper Kotmale tunnel of 12.9kms, which is the longest in Sri Lanka

was opened by President Mahinda Rajapaksa in November 2010.

All measures are in place to generate 409 gigawatts annually with a permanent capacity of 150 megawatts. The whole electricity generating procedure will be carried out in an eco-friendly manner.

All measures are in place to add the electricity generated by the Upper Kotmale Hydro Power Plant to the national grid within the first two weeks of next month.
 




 

 
 
   
   
    KS
006
   
   

top

   

Contact Information:: Send mail to priu@presidentsoffice.lk with questions or comments about this web site.
Last modified: May 11, 2012.

Copyright 2008 Policy Research & Information Unit of the Presidential Secretariat of Sri Lanka. All Rights Reserved.