News Line

    Go to Home Back
Email this to a friend
Printable version
Tuesday, September 16, 2014 - 4.54 GMT

Sri Lanka, China Presidents commission last phase of Norochcholai Power Plant

 

 

 

 

 

 

 

 

Electricity bill to go down by 25%, petrol, diesel and kerosene prices also reduced

President Mahinda Rajapaksa and Chinese President Xi Jinping together commissioned the last phase of the Norochcholai Lakvijaya Power Plant this evening at a joint event that remotely linked the Presidential Secretariat with Norochcholai via a fibre optic network.

Work on the second phase of Sri Lanka’s only coal-fired power plant commenced in March 2010.
Through this final phase, two generators of 300 MW each will contribute 600 MW, which will be sent through high voltage transmission lines to Anuradhapura through 234 electrical towers.

The first phase, which was completed in March 2011 and commissioned by President Rajapaksa, generates 300 MW of electricity that is being transmitted from Norochcholai to Veyangoda. In total, the Norochcholai plant now produces a total of 900 MW of electricity.

According to the Ministry of Power and Energy, from July 2011 to December 2013, the plant has generated approximately 3,646 GWh of electricity to the national grid, saving the country approximately Rs. 65 billion.
The project was completed with a concessionary loan by China Exim Bank. The cost of the entire project is US$ 1,346 million. The first phase cost US$ 455 million, and the second phase cost US$ 891 million.
High-level officials from both countries joined the two leaders for the commissioning ceremony at the Presidential Secretariat.

The Norochcholai Power Plant will further improve Sri Lankans’ access to electricity. Access to power has improved throughout the country in recent years, including the North and East. In February 2013,
President Rajapaksa commissioned the 24 MW Janani Power Plant in Chunnakam in Jaffna. That project helped provide uninterrupted power supply to the Jaffna and Kilinochchi districts.

The total percentage of households in Sri Lanka that have access to electricity has increased from 76.7 percent in 2005 to 97 percent in 2014.

Sri Lanka’s second coal-fired power plant will be constructed at Sampur in Trincomalee and is expected to add a further 500 MW to the national grid.

Following the commissioning of the power plant President Rajapaksa announced a reduction in the electricity bill, petrol, diesel and kerosene prices.

Electricity bill will be reduced by 25% while prices of petrol, diesel and kerosene will go down by Rs. 5, 3 and 20 respectively.
 

 
 
   
   
    SS
   
   

top

   

Contact Information:: Send mail to priu@presidentsoffice.lk with questions or comments about this web site.
Last modified: September 16, 2014.

Copyright © 2008 Policy Research & Information Unit of the Presidential Secretariat of Sri Lanka. All Rights Reserved.